For most project this is all you will need.
Revit replace window with door phasing.
Infill elements for earlier phases.
You add a skylight to the roof in phase 2.
Element was created in the phase of the current view.
Wanting to know how to control the display of elements based on their phase status in revit.
By nature revit infill s the demo phase but the infill itself doesn t have a phase assigned.
To access all phases options go to phases menu in the manage tab.
My first task is to delete all windows and doors and replace them with openings.
We would like to have the plans of.
The existing windows the destruction plan with the existing windows in red the project plan with the new windows the problem is.
If you place an insert into a host in a phase later than the host s creation phase revit lt creates an infill element for earlier phases.
We are trying to find the quickest way to replace windows in a renovation project.
In most revit templates the basic phases are existing and new.
For example you create a roof in phase 1.
Element was created in an earlier phase and continues to exist in.
Download window revit families for free with bimsmith.
If different phase property values are assigned to host and insert an infill element will be created.
The issue at hand is the phase communication between the demo and new.
There are hundres of windows and doors in the model and if i just delete the door or window the opening disappears with it.
This cannot be deleted or edited separately for changing phase property value.
A common mistake is to create a demolition phase.
I m doing a project for a construction company and i have to do a construction model in revit 2013.
Need to know correct workflow for managing phasing.
A phase filter is a rule that allow to apply a view to control the display of elements based on their phase status.
You look at the roof and skylight in a 3d view.
The wall infill s the demolished window and then when new window of same size location is added it confuses the model.
The phase property of the inserts door or window opening can differ from the walls phase.
Get the highest quality bim content you need from the manufacturers you trust.
In the projet the idea is to demolish the existing windows keep the hole and place a new window on the outside of the wall.